Trainee facing · Read aloud
Current situation
The 713th Contracting Squadron (713 CONS) is conducting an organized preproposal site visit for the $38.40 million Cargo Pier Fender and Corrosion Repairs task order under SM-MACC-01. Representatives of SM-MACC-01 holders attend. During the walkthrough, you notice a Diamond Dogs Civil Works, LLC representative has pulled SSgt Olga Gurlukovich of the Logistics Readiness Squadron (713 LRS) aside for a private conversation near the east cargo apron.
When you ask what they discussed, SSgt Gurlukovich explains that Diamond Dogs asked when the east cargo apron would be available for crane staging, material laydown, and contractor equipment. She says she merely told the representative that the apron will be unavailable from 14 through 25 June 2027 for the summer sealift but available on the other contemplated staging days, subject to ordinary daily Port Operations controls. That schedule does not appear in the task-order solicitation.
Trainer only · Do not issue
Facilitator context
Release as a short standalone inject at Increment 6. SSgt Gurlukovich's schedule is accurate; the defect is the unequal Government disclosure after solicitation release. The schedule affects means and methods, crane reservations, sequencing, price, and the technical approach. RFO FAR 15.101(d) says acquisition information necessary to prepare proposals that is disclosed to one or more potential offerors should be made publicly available as soon as practicable to avoid an unfair competitive advantage. RFO FAR 16.507 supplies the MACC fair-opportunity rule.
The strong response is to immediately provide the same schedule through the common task-order channel to every SM-MACC-01 holder while proposals can still account for it. Release N-04 only if trainees ask for the exact schedule or its accuracy. N-02 and M-03 already identify the complete MACC pool, so no separate distribution-list handout is needed. No draft notice is needed and trainees do not prepare one.
If trainees leave the exchange alone, Diamond Dogs later wins. A disappointed holder's postaward FOIA request reveals the private disclosure, and Diamond Dogs' technical approach aligns precisely with the unpublicized schedule. The holder files a timely GAO protest alleging a prejudicial breach of fair opportunity. The $38.40 million value places the modeled DoD order above the task-order protest threshold; the Government takes corrective action and reopens the competition, delaying the pier work and incurring protest and reevaluation effort. Keep this consequence within [N]; no later branch follows.
Trainer clue bank
Regulatory signposts
5 sourcesDirect trainees to a citation when they need a narrower clue. Have them apply the contract’s actual clauses, current thresholds, local policy, and the facts before treating any signpost as dispositive.
- RFO FAR16.507-2Fair-opportunity proceduresClue: Ask whether every multiple-award contract holder received a fair opportunity under procedures tailored to the order's risk and complexity, or whether a written exception under 16.507-6 applies. Separately confirm under 16.506 that the order is within the base contract's scope, ordering period, and maximum value.↗
- RFO FAR16.508Protests of ordersClue: The modeled $38.40 million DoD task order exceeds the applicable task-order protest jurisdiction threshold, so a disappointed MACC holder may protest the issuance at GAO. Use this only after trainees first identify the underlying unequal disclosure and prejudice; jurisdiction does not cure the fair-opportunity defect.↗
- RFO FAR15.101(d)Proposal-preparation informationClue: If acquisition information necessary to prepare proposals is disclosed to one or more potential offerors, RFO FAR 15.101(d) says it should be made publicly available as soon as practicable to avoid an unfair competitive advantage. For [N], apply that principle through RFO FAR 16.507 fair-opportunity procedures rather than assuming RFO FAR part 15 governs the order.↗
- RFO FAR15.106Amending a request for proposalClue: When a verified answer changes a material requirement, term, condition, or proposal assumption, issue the change to all eligible competitors and consider whether the response deadline must move. Use the actual MACC task-order amendment procedure; this is a useful RFO principle, not a statement that RFO FAR part 15 automatically governs the order.↗
- DoD RFO216.507Additional ordering procedures for multiple-award contractsClue: Check the DoD supplements to the RFO FAR ordering rules, including applicable debriefing and order-placement requirements.↗