Trainee facing · Read aloud
Current situation
Civil Engineering (713 CES) requires complete design and renewal of the approximately 18,000-square-foot Shadow Moses Command Post before the building returns to full operation. The firm-fixed-price task order will renew the roof and envelope, mission and support spaces, resilient power, HVAC, communications pathways, life-safety systems, and immediate security sitework. The Government has described the required square footage, room capacities, performance capabilities, fixed-barrier concept, and turnover date—but it has not furnished a building design. Nearly all architectural and engineering design remains with the design-builder after award.
The requirement is being competed through the one-step turn-key authority in 10 U.S.C. § 2862: SM-MACC-01 holders submit concept design and price together, and the resulting firm-fixed-price order will include both design and construction. The task-order request uses a best-value tradeoff and tells offerors that Technical Approach is most important, followed by Management Approach; Schedule and Past Performance are equal and next; Key Personnel follows; and the combined nonprice factors are significantly more important than Price.
Three holders submitted proposals. Diamond Dogs Civil Works, LLC offers the highest-rated and highest-priced concept; Militaires Sans Frontières Construction JV offers a balanced mid-price concept; and Gray Fox Systems, Inc. offers the lowest price and earliest turnover with less system redundancy and a weaker recent performance record. Each proposal includes a different floor arrangement, entrances, system routes, roof and wall materials, management and schedule approach, key personnel, relevant past performance, and firm-fixed price. Recommend the proposal that represents the best value and explain the tradeoffs supporting your recommendation.
Trainer only · Do not issue
Facilitator context
Release at Increment 11 with [H]. Begin as a source-selection exercise. The intended initial best-value leader is Diamond Dogs: its $275,000 premium over MSF and $625,000 premium over Gray Fox is supported by the strongest resilient systems, integrated design controls, key personnel, and relevant performance when combined nonprice factors are significantly more important than price. Accept a different ranking only if trainees articulate a coherent tradeoff using the announced factors rather than substituting lowest price.
The competition is a firm-fixed-price, one-step turn-key design-build order under RFO FAR 16.507. Treat the Command Post as an authorized military construction project: RFO FAR 36.002(c)(3) permits another procedure authorized by law, and 10 U.S.C. § 2862(a)(1) and (b)(1) authorize selection in one step on price and other criteria using Government performance specifications. The $4 million limit in § 2862(a)(2) applies only to repair projects. RFO FAR 15.103-1 supplies the announced tradeoff model, but RFO FAR part 15 procedures do not automatically govern this order.
The ranking exercise is deliberate misdirection. G-03, G-04, and G-05 put their west fixed-boulder lines 36, 40, and 44 feet west of Building 100. H-03 later establishes a fixed road envelope 28 to 52 feet west of the same wall, so every line occupies the future north-south fire lane. After the team recommends an awardee, ask whether a common assumption is safe merely because it appears in all offers. A combined review before award permits an equal written amendment, revised proposal designs and prices, and reevaluation without contractor reliance. Awarding any concept first means the boulders are installed in the road corridor and produces a Government-directed change, relocation work, additional Government cost, and avoidable schedule effect. State the consequence in [G]; do not release a separate outcome event.
Trainer clue bank
Regulatory signposts
13 sourcesDirect trainees to a citation when they need a narrower clue. Have them apply the contract’s actual clauses, current thresholds, local policy, and the facts before treating any signpost as dispositive.
- U.S.C.10 U.S.C. § 2802Military construction projectsClue: For a separately authorized MILCON project, confirm project authorization, purpose, current-year availability, and amount before treating a MACC order as executable. Cost and contract vehicle are separate questions; the vehicle does not replace project authority or funds.↗
- DoD FMRDoD FMR Vol. 3, Ch. 13, ¶ 3.2.1.1Periods of availabilityClue: Use this as the exercise timing baseline: most O&M appropriations are one-year authority, while military construction appropriations are normally five-year authority. In FY27, modeled MILCON from FY23 through FY27 may remain current for new obligations; later exercise purchase requests may deliberately cite FY24.↗
- RFO FAR16.507-2Fair-opportunity proceduresClue: Ask whether every multiple-award contract holder received a fair opportunity under procedures tailored to the order's risk and complexity, or whether a written exception under 16.507-6 applies. Separately confirm under 16.506 that the order is within the base contract's scope, ordering period, and maximum value.↗
- RFO FAR16.507-5Best-value order evaluation and documentationClue: Because the modeled order exceeds $7.5 million, check that the fair-opportunity notice gives a clear requirement, a reasonable response period, the significant factors and subfactors—including price—and their relative importance. The file must document the placement decision, price, and any tradeoffs supporting best value.↗
- DoD RFO216.507Additional ordering procedures for multiple-award contractsClue: Check the DoD supplements to the RFO FAR ordering rules, including applicable debriefing and order-placement requirements.↗
- RFO FAR15.103-1Tradeoff processClue: Use the tradeoff method adopted by G-02: award need not go to the lowest price or highest technical rating; a price premium must be justified by benefits that merit its cost, and the rationale must be documented. RFO FAR 16.507 governs the order, so do not imply that RFO FAR part 15 procedures automatically apply.↗
- RFO FAR15.104; 15.202Proposal evaluationClue: Evaluate only the factors stated in G-02. Compare technical and management approaches, schedule, key personnel, past-performance relevance and trends, and price; do not silently convert the competition to lowest price.↗
- RFO FAR36.002(c)(3)Design-and-construction procedures authorized by lawClue: RFO FAR 36.002(c) allows design-bid-build, two-phase design-build, or another acquisition procedure authorized by law. For [G], the third route points to 10 U.S.C. § 2862 rather than requiring a two-phase selection.↗
- U.S.C.10 U.S.C. § 2862(a)(1), (b)(1)One-step turn-key selection for authorized MILCONClue: Treat the Command Post as an authorized military construction project. Section 2862 permits one-step selection on price and other evaluation criteria for a firm-fixed-price contract covering both design and construction from Government performance specifications. The $4 million limitation in subsection (a)(2) applies to repair projects, not the authorized MILCON authority in subsection (a)(1).↗
- RFO FAR15.106Amending a request for proposalClue: When a verified answer changes a material requirement, term, condition, or proposal assumption, issue the change to all eligible competitors and consider whether the response deadline must move. Use the actual MACC task-order amendment procedure; this is a useful RFO principle, not a statement that RFO FAR part 15 automatically governs the order.↗
- RFO FAR52.236-8Other ContractsClue: Ask what coordination duties apply when Government personnel or other contractors work at or near the same site.↗
- UFC / UFSUFS 4-022-02Selection and Application of Vehicle BarriersClue: Use as a technical coordination signpost: the CO should obtain qualified security and engineering analysis of barrier layout, performance, and site constraints.↗
- UFC / UFSUFC 4-010-01Antiterrorism, Force Protection and Security EngineeringClue: Ask which current force-protection criteria and qualified technical approvals control the requirement before changing a security design.↗